Costa Mesa approves $19.4M Fire Station No. 2 rebuild, amid pushback on financing
- Share via
Replacing Costa Mesa’s Fire Station No. 2 has been on the city’s improvement list for years, but city officials only recently executed the necessary paperwork on a total rebuild anticipated to cost $19.4 million and take about two years to complete.
While most residents support the idea of upgrading the 80-year-old facility, some during an Oct. 20 Costa Mesa City Council meeting questioned the city’s signing off on the work and financing without seeking more public input.
Located at 800 Baker St., the 6,600-square-foot station is due to be completely demolished and replaced with a 9,445-square-foot, LEED Gold-certified facility with more capacity for updated equipment, new living quarters and a larger truck bay.
The new structure, which could be completed by early 2029, will feature a new kitchen and dining room, outdoor patio and eight dormitory rooms with four jack-and-jill restrooms, utility and storage rooms, an exercise facility and conference room as well as a public lobby.
Senior engineer Arash Rahimian told the council that Santa Clarita contractor AMG & Associates came in with the lowest appropriate bid, at $14,821,000 with a 10% contingency fee. The bid was protested by two other firms, but their objections were overruled by city staff.
During the demolition and construction, local fire personnel will be housed on site in temporary living quarters and then moved back in while the remainder of work on the building’s north end continues. Rahimian confirmed the relocation and rehousing costs were included in the total project estimate.
Resident Ralph Taboada, a member of the city’s Finance and Pension Advisory Committee, questioned why a project that’s been discussed for five years still hasn’t broken ground.
“Why has it taken five years to get to this point?” he asked. “Something needs to be approved, and I know this is going to be approved. But it just bothers the hell out of me that this is acceptable.”
After unanimously supporting the building contract and extending the terms of a handful of professional service agreements with an architecture and engineering firm and a community workforce administrator, the council moved on to the project’s financing.
Councilmembers authorized issuing between $14 million and $16 million in lease revenue bonds to finance the bulk of the Station No. 2 rebuild. To repay the notes, the city has pledged at least $1.13 million annually over a 20-year leaseback period, though that’s just an estimate.
The city will begin making interest payments in April 2027 with principal amortization set to begin that October. Under the proposed schedule, bonds will mature on Oct. 1, 2046.
Anna Sarabain, principal of the Irvine financial planning firm, said the city would initially pledge Fire Stations No. 1 and 2 as collateral, given the value of the Baker Street station will steeply decline during demolition. Then, as the new structure was built, Station No. 1 would be dropped from the agreement.
She explained Costa Mesa’s AA+ credit rating would likely qualify the city for an anticipated interest rate of 5%, about the best possible deal given current market conditions, and could explore refinancing after 10 years if favorable conditions returned.
Still, the financing strategy drew criticism from residents who expressed concern with borrowing big balances during a less-than-ideal economy for a project that’s been on Costa Mesa’s wishlist for several years.
“We need to know what the full cost of this financing is,” said Cynthia McDonald. “It’s not just the construction, it’s the construction plus years, potentially decades, of interest payments and underwriter expenses.”
They further questioned why the city did not run the plan past FiPAC members, whose role is “to advise the City Council in advance of significant votes, on issues related to significant financial matters.”
“I completely support issuing the bond. But this really should have gone to FiPAC,” said resident Jenn Tanaka, who formerly served on the committee. “There has been a pattern of deciding to move on projects and deciding there’s a very short timeline and then cutting public committees out of the process.”
Councilmember Mike Buley acknowledged the haste, but said he was hopeful a citywide facilities master plan currently being drafted will help identify needed upgrades and funding sources with enough lead time for optimal budgeting.
Ahead of a 7-0 vote, Mayor John Stephens said the work is undoubtedly necessary.
“We’ve got a tight time frame,” he said. “Maybe it should have been done a long time ago. [But] there’s nothing we can do about that. It’s worthwhile, and we need to pay for it.”