California still hasn’t bought land for bullet train route

Share

Construction of California’s high-speed rail network is supposed to start in just six months, but the state hasn’t acquired a single acre along the route and faces what officials are calling a challenging schedule to assemble hundreds of parcels needed in the Central Valley.

The complexity of getting federal, state and local regulatory approvals for the massive $68-billion project has already pushed back the start of construction to July from late last year. Even with that additional time, however, the state is facing a risk of not having the property to start major construction work near Fresno as now planned.

It hopes to begin making purchase offers for land in the next several weeks. But that’s only the first step in a convoluted legal process that will give farmers, businesses and homeowners leverage to delay the project by weeks, if not months, and drive up sales prices, legal experts say.

Continue reading >>

-- Ralph Vartabedian, Los Angeles Times