Asphalt repaving is planned for next week...

Asphalt repaving is planned for next week as part of the Downtown

Area Street Rehabilitation Project. Resurfacing work on Third Street

and Ocean Avenue is scheduled for April 28. Repaving on Second, Beach

and Mermaid streets, as well as Park and lower Forest avenues and El

Paseo is planned for April 29. More paving is planned in an alley off

Third Street and the city’s downtown parking lots on April 30.

Repaving on upper Forest Avenue is scheduled for the first week of

May.

Pavement will be ground down two days before repaving. All asphalt

work will occur between 7 a.m. and 4 p.m. Trash collection will be

before 7 a.m. Traffic congestion and delays are expected during. Work

is scheduled to continue on the project through May.

Installation of the Louise Street storm drain will result in a

lane closure on North Coast Highway through mid-May. The work will be

on the area between Ledroit Street and East Mesa Drive. The No. 2

lane will be closed from 9 a.m. to 3 p.m. Monday through Friday

during construction.