Police building claims at $22M
- Share via
Darleene Barrientos
The new Glendale Police Headquarters, already nearly two years behind
schedule, might result in expensive litigation -- $20 million in one
case -- for the city. And no date has been set for the department to
move into the building.
A claim for an additional $20 million was filed by the project’s
general contractor, Ray Wilson Co., demanding payment for work that
had to be done outside the scope of the original contract. A claim
must be submitted to a city before a lawsuit can be filed.
At least two lawsuits by subcontractors demanding more than $2
million from the city also have been filed, City Atty. Scott Howard
said.
Subcontractors Rutherford Co. Inc., which worked on the building’s
drywall installation, and ISEC Inc., which did much of the carpentry,
filed notices with the city of Glendale and Ray Wilson Co., claiming
they were not paid for their work, according to court records. The
city has withheld the funds, which total about $2.3 million, and
probably will resolve those lawsuits out of court, Howard said. He
declined to give specifics on how the lawsuits will be settled.
The disputes stem from the extra time it has taken to finish the
building, which meant extending the contracts of several consultants
including Koury Inspection & Testing Inc. of Gardena; Vanir
Construction Management of Los Angeles; and Cannon Design Architects
of Los Angeles. The revised contracts have cost the city hundreds of
thousands of dollars in revisions.
The original cost of the building was $33.6 million. Recent cost
estimates are between $35 million and $40 million.
“The city and Ray Wilson have some significant disagreements and
fundamental differences in regard to what each party is obligated to
under the contract,” said Chuck Gossage, an attorney representing Ray
Wilson Co.
Ray Wilson Co. is demanding $20 million from the city for what it
believes were project delays and work done outside the scope of the
original contract. The work done was too numerous to detail, Gossage
said, adding that during the past three years, the city asked for
1,100 change orders.
The police department just wants to move into the building, Budget
Administrator Jay Kreitz said. But with security, phone and
public-address systems still down, it is not possible to allow the
more than 300 people who work for the department to move in. Police
and city officials declined to estimate when the building will be
ready.
Most buildings can have construction workers doing finishing
touches as employees work, but not a police station, Kreitz said.
Thousands of finishing touches are needed and workers at a police
station need to be watched and escorted everywhere they go, Kreitz
said.
“Who would watch them?” he said.