No one can accuse Traylor Bros. of ducking tough assignments.

The construction firm chosen by the Metropolitan Transportation Authority to dig twin subway tunnels through the Hollywood and Studio City hills has taken on some of the nation’s most daunting jobs: In the past few years alone it excavated two tunnels for the superconducting supercollider and erected the nation’s longest cable-stayed bridge in Texas.

Seldom, however, have expectations been so high for the Indiana-based firm and its partner, Frontier-Kemper, as when engineers will lower 48 truckloads of parts into an 80-foot shaft in Studio City next month to assemble two tunnel-boring machines.

The two 2.6-mile hard-rock tunnels that those mechanical moles will excavate will become the first critical test for the new management of the troubled MTA, a transit agency buffeted by construction fiascoes, cost overruns and political infighting that led last week to the firing of Franklin E. White as chief executive.

Advertisement

And the tunnels will test the mettle of the Traylor/Frontier corporate team, which has recently had its reputation dented by the collapse of a floating bridge in Seattle, a waterlogged light-rail tunnel in Portland, Ore., and Oregon officials’ accusations of indifference to worker safety.

Traylor officials, who are managing the project, are prohibited by the MTA from talking about the Los Angeles tunnels. But others have not been silent about their views of the contractor’s role.

At an MTA board of directors meeting Wednesday, Los Angeles County Supervisor Mike Antonovich and state Sen. Tom Hayden (D-Santa Monica) called unsuccessfully for a halt to tunneling until the firm’s safety record is investigated.

“How was the decision to employ Traylor Bros. . . . ever justified?” Hayden wrote in a letter to the board last week.

MTA construction executive Stanley Phernambucq countered Antonovich and Hayden by arguing that Frontier-Kemper, not Traylor, managed the Portland joint venture. He also said his staff studied Traylor’s track record before granting it the Red Line contract.

“Safety is priority No. 1 in my outfit,” he said.

Los Angeles City Council President John Ferraro has separately demanded in a letter that the boring machines remain silent until the MTA drafts a new report studying the likely environmental impacts of the tunnels on the flora and water table of Runyon Canyon Park, a Hollywood Hills landmark.

Advertisement

Phernambucq on Wednesday dismissed that concern, saying it was covered in the MTA’s original environmental impact reports.

Within the MTA, however, several questions are being raised about Traylor Bros.’ efforts. The MTA last week ordered the firm to abandon its plans to store 10,000 pounds of explosives in a completed tunnel under Hollywood after learning that Cal/OSHA officials were not likely to permit it.

Also, an MTA board member has expressed dismay over what he considers the scant number of deep test borings the firm has ordered to determine the type of rock and amount of water in the mountains.

Meanwhile, skeptical hillside homeowners--who are being asked to sign away subway easements 200 to 800 feet beneath their properties, and to endure explosives blasts 15 hours a day for 14 months--are asking a more fundamental question:

Just what kind of an outfit is Traylor Bros./Frontier-Kemper?

Traylor Bros., a family-owned firm founded half a century ago in Evansville, Ind., was the 127th largest construction contractor in the United States last year with $166 million in revenues, according to the trade journal Engineering News-Record. Frontier-Kemper, a largely German-owned firm also based in that southern Indiana city, ranked 265th.

But even relatively small firms get major work because the job of building and refurbishing the country’s infrastructure is so vast. While the $126-million Red Line tunnels hold Los Angeles’ attention, Traylor is also building a $61-million highway in Texas and a $70-million bridge in Florida.

Advertisement

*

Despite success in attracting new business, Traylor Bros. continues to be shadowed by a wildly stormy night in Seattle five years ago. In one of the most spectacular engineering failures in that state’s history, an old interstate highway bridge the firm was renovating sank into Lake Washington after three steady days of rain.

The state sued Traylor for $69 million, complaining that poor construction work had cracked a pontoon in the middle of the floating bridge. The company countersued, asserting that the state had “fraudulently concealed” the extent of the bridge’s deterioration.

Traylor paid the state of Washington and the federal government $20 million in a 1992 settlement that did not assign blame. Yet state Department of Transportation inspectors’ accusations of disorganization, in documents published by the Seattle Times, stung the company.

“The charges were totally false,” said Roger Foreman, general manager of Traylor Bros., in an interview with the Los Angeles Times. “We pride ourselves on doing good work, and we always want to walk away from a project having earned the respect of the owner. Any time you fall short of that it’s disappointing.”

More recent, Traylor Bros. and Frontier-Kemper have grappled with delays and cost overruns in a Portland, Ore., light-rail tunnel strikingly similar to the one planned for the Hollywood Hills.

Managed by Frontier-Kemper, the job was won by a low bid of $103 million. But unanticipated obstacles have caused delays of nearly a year. In turn, the price tag has skyrocketed to $160 million, according to Jan Schaeffer, spokeswoman for Tri-Met, the Portland transit agency. One change order alone pushed the cost up $26 million, she said.

Advertisement

Unexpectedly brittle rock led to months of delays. Unexpected water flooded into the tunnel, creating a mucky mess that local newspapers called “Waterworld.” The contractors and Tri-Met battled almost daily over the response.

Tri-Met officials admit that their engineers misjudged the rock. But University of Alberta civil engineering professor Dan Eisenstein, a tunneling expert hired by the MTA to study the Portland project, said in an interview that Frontier/Traylor may not have adapted quickly enough.

In fact, Schaeffer said Frontier and Traylor negotiators at first engaged in macho “posturing” over their culpability in the delays.

“We’ve at least worked it out now to where we aren’t fighting each other,” she said.

Foreman, the Traylor Bros. general manager, acknowledged “major differing site conditions” that resulted in delays. “The remedies for those conditions have been worked out between the contractor and the owner,” he said. Oregon’s Occupational Safety and Health Administration fined Frontier/Traylor $116,500 for negligence in one worker’s death in the Portland tunnel project.

In that case, Jacques G. Mathieu, a 39-year-old foreman, perished in March after he accidentally flipped a remote-control switch that caused the hydraulic arm of a machine to crush him. Oregon OSHA said the machine, which positioned steel ribs on tunnel walls, was a prototype that had not been fully tested.

Oregon OSHA has fined Frontier/Traylor $34,125 in 40 other safety violations considered serious enough to potentially cause significant physical harm, according to spokeswoman Jan Wagner.

Advertisement

Foreman said all the fines are being appealed.

*

Portland also provided a laboratory for Frontier and Traylor in the way underground explosives are felt in neighborhoods--an important concern in Los Angeles, where blasts will take place beneath homes and Runyon Canyon Park.

Frontier/Traylor halted nighttime explosions in Portland after three weeks of complaints last year, then installed heavy rubber blast doors at the tunnel’s mouth to contain the noise. Tri-Met also gave hotel vouchers to residents who still felt rattled.

Schaeffer, the Portland transit agency’s liaison, said shallow explosions felt like a “rolling underground thunder” that caused no structural damage to homes. She said homeowners directly above the blasts felt much less than homeowners downwind of the tunnel’s mouth, and that effects were minimal once the hole sank past 200 feet.

“We learned that it’s hard to predict how sound and vibration will travel,” she said.

Still, Frontier-Kemper and Tri-Met took two precautions that Traylor Bros. and MTA initially forswore in Los Angeles.

In Portland, the tunneling contractor has never stored more than a day’s supply of explosives at its construction site. And Tri-Met drilled 80 test borings over the three-mile tunnel route to better understand the rock below, according to Schaeffer.

Here, Traylor Bros. asked Cal/OSHA for permission to store a week’s supply of explosives in a tunnel. The state rejected the application without review because of the danger that workers could be trapped in an explosion, said Richard Hughes, principal safety engineer at Cal/OSHA’s mining division. MTA officials have told Traylor not to appeal the ruling, according to a spokesman.

Advertisement

Instead, a subcontractor will make daily deliveries of emulsion-gel explosives during the 14 months of blasting unless an alternative method of carving out the underground rooms is conceived.

The MTA has also only drilled 25 test borings to examine the rock strata 800 feet below ground over its route near the Cahuenga Pass--about half as many as some mining experts consider prudent. The agency says 1950s-era water and sewer tunnels that traverse the same area at a shallower depth provide data that additional borings would provide.

Board member Nick Patsaouras rejected that view. “The staff should spend as much as it takes to make as many borings as possible,” he said. “What’s another few million dollars if it makes this a safer job?”

Foreman of Traylor Bros. disagreed, saying that the Santa Monica Mountains rock is “not really as complex” as Portland’s. “It’s a known geology and we don’t anticipate any problems,” he said.

Indeed, many knowledgeable construction industry professionals believe that Traylor will perform well in the Santa Monicas.

“They are one of the finest half-dozen tunneling contractors in the United States,” said John Shea, president of the construction firm that helped to dig tunnels in Hollywood. “The MTA is lucky to have them.”