Nuclear Agency Faulted for Review Process

Share
From Associated Press

The Nuclear Regulatory Commission has failed to adequately ensure that owners of nuclear power plants have enough funds to safely own, operate and later decommission the facilities, according to a congressional review.

The commission needs to tighten its review process for license transfer requests, especially because the future costs to dismantle a plant and dispose of radioactive waste could increase, said the study by the General Accounting Office, the investigative arm of Congress.

The review was requested by Rep. Edward J. Markey (D-Mass.) because of concerns that deregulation and license transfers have affected decommission funds. Costs of decommissioning can run to $400 million per plant.

Advertisement

The NRC has licensed 125 nuclear power plants for a limited time. Utilities have sold or are in the process of selling all or part of 15 plants; 30 other plants have had licenses transferred.

Before transferring a license, the commission requires companies to have funds available either by making periodic deposits into a trust fund; prepayment; obtaining a surety bond, insurance or credit; or guaranteeing payment if a parent company can meet certain financial requirements.

In general, enough money is being set aside to eventually take a plant out of service, the report said. But the NRC hasn’t done enough to monitor the financial arrangements, it said.

The commission’s “reviews were not always rigorous enough to ensure that decommissioning funds would be adequate,” the report said. “Moreover, NRC did not always adequately verify the new owners’ financial qualifications to safely own and operate the plants.”

The NRC should request guaranteed additional revenue sources and document its review of any financial information, including revenue projections, the report said.

Also, the report said the commission now allows plant owners to wait too long--about two years--before their licenses are terminated to perform radiological assessments to determine what additional cleanup might be needed. The GAO recommended the commission move up that deadline.