Test Mishap Delays Development of Lockheed’s X-33 Rocket Plane

Share
TIMES STAFF WRITER

Lockheed Martin Corp.’s assembly of a next-generation space shuttle has stumbled on yet another technical snafu, potentially delaying the prototype’s first test flight an additional six months or more, sources said.

Development of the X-33 rocket plane, which is overseen by Lockheed Martin’s Palmdale plant, suffered the latest setback Wednesday night as a critical component underwent testing at NASA’s Marshall Space Flight Center in Huntsville, Ala.

A large section of the outer wall of one of the vehicle’s two liquid hydrogen fuel tanks separated about two hours after it had completed pressure and structural tests at the facility, sources said.

Advertisement

Technical snags and cost overruns are common in space projects, but the series of glitches that has plagued the X-33 for more than a year is threatening a program that NASA deems pivotal for its future. The space agency has placed a huge wager on Lockheed Martin’s technologically ambitious design, committing $941 million to X-33 development.

Under the National Aeronautics and Space Administration’s plan, the prototype would lead to development of a reusable launch vehicle called Venture Star that would cut the cost of space flight tenfold and replace the fleet of shuttles, which it aims to replace after 2012.

For Lockheed Martin, the latest delay all but ensures that it will be unable to have an operational Venture Star vehicle by the end of 2004, as it had promised to more than a dozen states competing to serve as the space port for the vehicle.

Before Wednesday’s mishap, the X-33’s first test flight was scheduled for July 2000.

“We’ve been very honest about how tough this is,” said one Lockheed Martin official, speaking on condition of anonymity. When the states understand details of the latest problem, “they’ll see this is the nature of a technology development program.”

Lockheed and NASA engineers have only started to survey the damage to the tank, and will erect scaffolding around it next week to permit a closer inspection, officials said.

Wednesday’s snafu marks the second time one of the graphite-reinforced plastic tanks has run into trouble in the manufacturing process. The inner skin of the X-33’s other liquid hydrogen fuel tank separated while it was being bonded last December.

Advertisement

Examiners with the General Accounting Office, the investigative arm of Congress, have criticized the project for its rising costs and had already warned that delays in the prototype would harm NASA’s plans for a full-scale reusable vehicle.

GAO officials said in a report released in August that technical setbacks to that point had increased the cost to taxpayers by $317.6 million--even though the prototype will deliver less than initially promised.

For example, the prototype will use an internal liquid oxygen tank made of aluminum, instead of lightweight composites as envisioned earlier. But the full-scale Venture Star will probably need to have a composite tank in order to be light enough to reach orbit, GAO said. Examiners questioned whether the X-33 would effectively lead to development of the more advanced full-scale vehicle.

Responding to Wednesday’s snafu, NASA officials released a statement saying the space agency “is committed to developing advanced space transportation; a commitment which includes looking at alternative technologies to ensure the success of X-33.”