Victoria Avenue to Be Partially Closed

Share

Two lanes in each direction on Victoria Avenue will be closed Monday and Tuesday for repaving between 7 a.m. and 5 p.m.

Two lanes in each direction will also stay open.

The repaving is part of the final stages of the Ventura Freeway and Victoria Avenue interchange project that began in April 1998 and should be completed in February.

The $12.5-million project includes two new bridges, widening Victoria Avenue and Valentine Road, and the addition of southbound onramps and offramps.

Advertisement

For more information, contact construction manager Bob Stein at 218-6717.