Advertisement

Mitsubishi to Build Power Plant in Mexico

Share
From Bloomberg News

Mitsubishi Corp. of Japan signed a contract to build a $611-million coal-fired power plant for Mexico’s government-owned electricity company.

The plant will have the capacity to generate 651 megawatts of power and will take three years and eight months to complete, the Federal Electricity Commission said.

Mitsubishi will begin construction on the plant, in the southern state of Guerrero, on May 31, the commission said.