Advertisement

TAMING A LANDSLIDE : Residents, Rancho P.V. Clash Over Schedule of Road Work

Share
Times Staff Writer

Encouraged by what they view as a successful first phase of a $2-million program to tame the 31-year-old Portuguese Bend landslide, members of the Rancho Palos Verdes city staff are urging that the next segment of work get under way within a month.

Some residents of the area disagree, however, saying it is too soon to know whether the program is working.

The second phase will involve relocating the sliding Palos Verdes Drive South roadway onto more stable ground close to its original right of way.

Advertisement

“The big advantage to doing it this fall is that things have been dry and we are in good condition to move ahead,” said city geologist Perry Ehlig.

In a report to the city in June, Ehlig said that although movement continues in the slide, it is at a “greatly reduced rate.”

Massive Shifting

Officials attribute the slowdown to the massive shifting of 600,000 cubic yards of dirt from the top of the slide--where it was exerting downward pressure--to the bottom of the slide, where it could act as a block against further movement. As part of the $1-million first phase, drainage systems also were put in to prevent water from reaching the slide plane.

In the northern 50 acres of the 260-acre slide, the rate of movement--formerly 4.6 to 10 feet per year--has slowed to 1 or 1.4 feet and may have stopped altogether in some places, Ehlig said. Lower portions of the slide are moving faster but were slowed by the grading work. For example, Ehlig said, the 60-acre east-central portion of the slide, which is above Palos Verdes Drive South, is moving at half the rate it was three years ago.

More large-scale earth movement is proposed for the second phase, in which an additional 500,000 cubic yards would be taken from northern portions of the slide and placed on the new Palos Verdes Drive South roadbed to provide stability for the relocated road. The cost of that work is estimated at $500,000.

A lengthy environmental impact report on the slide work asserts that a safe alignment of the road--the only coastal road connecting Rancho Palos Verdes and San Pedro--is impossible in the present location. “Moving the road north, to as near pre-slide alignment as possible, would place it in an alignment that is moving much slower,” the report states.

Advertisement

According to the Ehlig report, the present road is in an area that is moving 23.8 feet and 32.9 feet a year at two monuments that measure movement. But land where the road will be moved to is moving from 7.3 to 14 feet a year.

Maintenance Costs

Relocation would cost $321,900, but the environmental report states that the $225,000 a year it currently costs the city to regrade and patch the ever-moving road would be reduced to $37,143 because of less land movement.

Charles Abbott, city public works consultant who is in charge of the stabilization project, favors the realignment. He said in terms of safety and maintenance costs, there is no comparison between keeping the present road and moving it.

The relocated road also would have a drainage system to pipe runoff directly to the ocean. According to the report, runoff from the present road goes directly into slide fissures and depressions and makes the movement worse.

During the life of the slide, the road has moved seaward in a curving direction, and the present road is as much as 350 feet away from where it used to be. The slide was triggered in 1956 by work on the Crenshaw Boulevard extension, which was immediately abandoned and never completed.

The City Council, sitting as the Redevelopment Agency, could give the go-ahead Nov. 4 after the public comment period for the extensive environmental impact report ends.

Advertisement

Inclined to Move Ahead

“Ehlig is strongly recommending that we move ahead, and the (agency) is, from my perspective, inclined to move that way,” said Mayor Mel Hughes.

Abbott said that with approval, the work could be under way by Nov. 15 and completed within 90 days.

But in Portuguese Bend, some residents say officials may not fully understand the landslide and are advising caution. In a letter to the city, resident Andrew H. Sargent, an attorney, said: “Prudence calls for a go-slow attitude. . . . To proceed without allowing sufficient time to pass to intelligently assess the impact of the previous actions is negligent.”

Longtime resident Jeanne Smolley said that because of recent dry years, it is difficult to know how much of the slowdown of the slide is attributable to the grading. “We would have to wait and see,” she said. “Water has a great deal of weight, and weight is the driving force.”

The road relocation appears to be a major sore point with Portuguese Bend residents.

“We are a small community . . . the people who live on the landslide and take care of it,” said Daphne Clarke of Peppertree Drive. “We are all pretty well agreed in favor of stabilization, but we don’t want the road (relocated). They can do the work with the road where it is.”

More than two years ago, Clarke, her husband and four other property owners filed suit against the city, alleging that the present Palos Verdes Drive South, as realigned over the years, encroaches on their property. They contend that their property lines have moved with their sliding land.

Advertisement

The city contends that although land may move, property lines do not and the residents no longer own the land they claim. The case is nearing a trial date, Clarke said.

One home, owned by builder Gene Frank of Cherry Hill Lane, apparently will have to be moved or demolished for the road project because it has slid too close to the original right of way.

Abbott said Frank and the city are negotiating whether the house will be moved or acquired by the city. Its appraised value is $133,000, Abbott said. At the same time, he said, the city has begun condemnation proceedings “so as not to get a big delay” if it cannot reach agreement with Frank.

Frank said he wants the house moved to other Portuguese Bend property he ownes on Narcissa Drive, but Abbott said the site is too far. Frank also said he disagrees with the city’s appraisal, setting the value of the house at “well over $250,000.” What the city wants to give him, he said, “wouldn’t buy a bungalow in Wilmington.”

Resident Smolley said opposition to the road work centers on the still unresolved questions about legal boundaries of land in Portuguese Bend that are raised in the Clarke suit.

Smolley and some others also said they are concerned about the panel of volunteer geologists recruited by Ehlig to advise the city on the landslide project.

Advertisement

“They may not review the data in as much depth as we think they should,” she said. “When you have volunteers, you’re not sure how many hours they can put in.”

The city last week investigated a 200-foot-long fissure, discovered by Smolley, at the urging of Portuguese Bend residents, who thought it might be a new landslide. “It may be nothing, but I thought it was something they should look into,” she said.

Ehlig this week said the fissure, above the northwest corner of the Portuguese Bend slide, is connected to an old slide. “Its cracking is associated with sliding that has occurred there in the past,” he said, adding that it is “nothing to be concerned about.”

Advertisement