Weeds grow and dust blows where there should be community swimming pools and landscaped neighborhoods.

The last phase of the 100-unit Baldwin Co. condominium project in Anaheim Hills was just being framed when the giant development company filed for bankruptcy last July and work stopped. Since then, the plywood sheathing on the buildings has weathered to a dull gray, maintenance in the completed part of the development has been sporadic and vandals have taken to cutting wiring and removing building supplies abandoned at the site.

Residents who bought before the bankruptcy find themselves staring out of their living room windows at the skeletal units, stuck in houses they can’t sell because of the state of their neighborhood.

Advertisement

“We have neighbors who can’t get their warranty repairs done, and we’re paying $96 a month in association fees to support a community center and a pool that have never been built,” said Jeff Sherwood, a 31-year-old UPS driver who moved into the development last May with his wife, Lisa, and their daughter, Lauren, now a 22-month-old toddler.

The once powerful development company’s downward spiral is being played out in Bankruptcy Court, but its impact goes far beyond the corps of lawyers, bankers and bond investors who line the benches during each hearing.

“They talk about paying debts,” said Sherwood, “but nobody worries about us.”

*

Baldwin Co. is out of money, and a continuing string of disputes with its lenders has kept its bank accounts empty since the bankruptcy was filed.

With few exceptions, Baldwin Co. hasn’t started work on a new home in almost nine months, company President Alfred Baldwin says. The company had 20 projects from San Diego County to Ventura underway when it entered bankruptcy, including half a dozen in Anaheim Hills and several in Portola Hills in southern Orange County.

Last week Baldwin and his brother, James, co-owners of the Newport Beach-based company, said they would not oppose a demand to put the company under the control of a court-appointed trustee. The company’s chief creditors made the demand after the collapse of a deal in which the Baldwins secretly had agreed to resign and be replaced by an executive from another Orange County building firm.

The hope is that new management will stand a better chance of finding investors who would be willing to purchase and complete unfinished projects, said creditors’ attorney David Frauman.

Advertisement

That would bring in money to pay off some of Baldwin Co.’s $245 million in debts. It also would bring relief to Baldwin homeowners who say they are the unrecognized victims of the bankruptcy.

“It’s a disaster,” said Joan Blackford, who bought her Baldwin-built Summit Park condominium in Anaheim Hills 19 months ago and says neighbors are now fighting neighbors over problems that stem from the bankrupt builder’s neglect of the 100-unit development.

Efforts to raise money by selling Baldwin Co. projects in Orange, San Diego, Los Angeles and Ventura counties to other builders or investors have bogged down as Baldwin’s title insurance company refuses to write policies for many of its properties.

The title situation not only has choked off bulk sales of Baldwin acreage but individual home sales as well, insiders say. In at least one condo development, some buyers who had opened escrow have pulled out and bought elsewhere. The lack of cash makes it impossible for Baldwin Co. to tend to its everyday business.

Alfred Baldwin declined to discuss problems at Summit Park or other Baldwin developments.

*

But Blackford says the situation is making life miserable for her and her neighbors.

Blackford and her husband, Rick, are still waiting for Baldwin Co. to repair a leaky front door and take care of other nagging problems reported last September and supposedly covered by the builder’s warranty.

Some of their neighbors, like the Sherwoods, paid $2,000 extra for lots that looked out on the Summit Park community swimming pool and recreation center. It was supposed to be done by now. Instead, after nearly a year in their home, the Sherwoods still view an empty dirt lot.

Advertisement

Summit Park residents also are waiting for the opening of the Baldwin-built park that gave their development its name.

Although apparently completed, the park remains enclosed by a tall fence that routinely is scaled on weekends by area residents desperate for a place for their kids to play. It is off-limits because Baldwin cannot clear the title and turn it over to the city. And without city liability insurance, it cannot be opened to the public, said Anaheim parks planner Dick Mayer.

But worse than the missing pool, closed park and lack of service to homeowners, says Blackford, is that the builder’s financial woes are keeping the development from becoming a community.

She said several of her neighbors have become so disgusted with lack of maintenance and warranty work that they are refusing to pay their monthly homeowner association dues. That has forced the association board to hire a lawyer to write threatening letters to the holdout homeowners.

“The dues help pay our fire insurance premiums among other things,” said Blackford, who is the association secretary and one of two Summit Park residents on the board. “This is turning neighbor against neighbor, and that is just not right.”

*

Baldwin Co., which by law retains control of the board until it has sold all of the lots in the development, stopped sending three of its four representatives to board meetings several months ago, making it difficult for the association to conduct business, Blackford said.

Advertisement

Alfred Baldwin acknowledged that the company and its creditors see the bulk sale of properties as the best way to raise cash.

He downplayed the title policy situation, however, calling it a minor problem.

But one lawyer involved in the bankruptcy says things are more serious than Baldwin will publicly admit. “We are at one of the many crisis points that keep coming up in this bankruptcy,” said the lawyer, who asked to remain unidentified.

Without title insurance, Baldwin can’t close escrow on individual homes, and outside investors won’t touch the company’s bulk assets, according to one of the bankruptcy lawyers.

First American Title Insurance Co. in Santa Ana is holding back title insurance because of liens placed on the properties by subcontractors who have not been paid for work they did. Baldwin Co. owes several million dollars to various subcontractors as part of its total debt, which includes $155 million owed to investors who bought Baldwin junk bonds in 1993.

First American, which declined comment on the insurance situation, reportedly wants Baldwin Co. to post a security bond or seek a court order that would remove the dozens of mechanics liens filed against Baldwin-owned properties.

Bankruptcy law permits a judge to shift liens from property titles to the proceeds from the sale of those properties. In that way, buyers would get clear title to land or homes while subcontractors would be paid before Baldwin Co. or its other creditors received whatever is left from the proceeds.

Advertisement

Baldwin Co., which does business as Baldwin Builders and Baldwin Building Contractors, filed for a Chapter 11 bankruptcy reorganization last July, claiming that its major lender at the time had stopped honoring its loan commitment and emptied Baldwin Co. bank accounts of about $13 million.

In February, Baldwin obtained a new $85-million loan and used $70 million to pay off the lender, General Electric Capital Corp. It used the rest to pay off bankruptcy expenses and some debts to subcontractors for work done during the bankruptcy. But the company hasn’t been able to generate enough cash from home and asset sales to keep all of its subcontractors on the job.

Baldwin also has not yet come up with a plan to reorganize prior debts.

*

The slow-moving court process provides little solace to Baldwin home buyers in half-finished projects such as Summit Park.

The third phase of the condo complex has been standing empty for months, Blackford said, and the partly finished buildings have drawn vandals who have cut wiring and stolen building materials from the site.

Despite that, the Baldwin sales office at Summit Park remains open and potential buyers still tour the models. The units are priced from $130,000 to $160,000. Blackford said several people who were in escrow on units in the development have canceled the deals and gone elsewhere.

The weathered skeleton of one of the unfinished buildings has framed a portion of the view from the Blackfords’ kitchen window for more than six months, she said.

Advertisement

Lisa Sherwood and her husband get the same view from their front windows. They also look out at the dusty lot that was supposed to house the community pool and recreation facilities.

Sherwood says the couple spends lot of time trying to explain to their daughter why she still doesn’t have an outdoor place to play except within their unit’s small fenced courtyard.

“It’s not fair. We’re paying our bills, but we’re not getting what we paid for,” Sherwood says. “This is our first house, lucky us.”