The City Council last week approved making the first payment on the Empty Saddle Drive, Spotted Pony Lane and Dillon Road street improvements. Council members voted 5 to 0 to pay All American Asphalt $184,000 toward the project, which began in January. Wet, saturated soil was uncovered during the reconstruction of Dillon Road and had to be removed; the extra work was not anticipated and cost the city an additional $1,700. The entire project will cost about $400,000.