Advertisement

EPA Plans for OII Site Could Postpone Mall

Share
Times Staff Writer

The U. S. Environmental Protection Agency has proposed a strategy for cleaning up the Operating Industries Inc. (OII) landfill that could delay Monterey Park’s plans for a retail center on 45 acres north of the Pomona Freeway until the next century.

The EPA also has announced that a plan proposed by Monterey Park and supported by Montebello to extend Greenwood Avenue through the dump to create a new freeway interchange will entail huge costs that the EPA cannot absorb. City officials said that unless the agency changes its position, the extension will not be built.

The EPA disclosed last week that it had found extensive soil and ground-water contamination on the 45-acre portion of the dump where Monterey Park had hoped to develop a retail center. The agency said it wants to use that land as the center for its cleanup activities at the dump.

Advertisement

A U. S. congressman and officials in the two cities voiced disappointment and, in some cases, anger with the direction the EPA is taking.

‘Concerned and Angry’

“I am really very concerned and angry,” said Monterey Park Mayor Christopher Houseman.

He said the EPA decision to cluster its cleanup activities on the 45 acres north of the Pomona freeway will, in effect, make that area a permanent site for the treatment of hazardous waste. Other cities will insist on sending their toxic waste to Monterey Park for treatment, he said, adding that he doubts the EPA will be able to keep its pledge to use the property only to treat waste from OII.

Montebello City Administrator Joseph Goeden said the plan to extend Greenwood Avenue from Monterey Park to Montebello and build on- and off-ramps at the Pomona Freeway was being counted upon to ease rush-hour congestion. Goeden said the interchange would reduce traffic on Garfield and Wilcox avenues at the freeway and ease a burden on residential streets used by commuters at peak traffic periods.

Rep. Matthew G. Martinez (D-Monterey Park) accused the EPA of ignoring the concerns of cities and residents. “EPA is not going to get away with this arrogant, Nazi-like attitude they have,” Martinez vowed. He said the agency’s latest decisions are contrary to its promises to work with cities and residents.

But Michele Dermer, EPA project manager, said the agency has consulted the cities and residents.

Studies Cited

She said the conclusions about the Greenwood extension and the proposal to put treatment and cleanup facilities on the 45-acre site grew out of detailed studies.

Advertisement

Dermer said the EPA found wider deposits of rubbish and more toxic contaminants on the property than had been reported by the city and the state Department of Health Services two years ago in their request to keep the 45 acres off the federal Superfund list.

The property was part of the OII landfill before the state built the Pomona Freeway through the area in 1968, severing the northern parcel from the remainder of the dump. The 45 acres are occupied by an auto salvage yard, a trucking company, a wood recycler and a pavement-crushing business. The 135-acre portion of the dump on the south side of the freeway was closed in 1984 amid complaints about odors and the dumping of toxic waste.

The city and state in 1986 proposed a plan that would have sold the northern 45 acres to a developer, generating $7 million for cleanup of the rest of the property. EPA officials rejected the plan and placed both OII parcels on its Superfund list. But the EPA agreed to analyze contamination of the 45 acres separately to determine whether that property could be cleaned up quickly and developed.

The city and state had contended that most of the contamination was confined to 6.5 acres where 110,000 cubic yards of trash were buried. But EPA said it found 400,000 cubic yards of trash buried as deep as 55 feet on 11 acres.

The study found potentially hazardous concentrations of lead and other contaminants in the soil.

Investigators drilled 12 wells and found organic contaminants in five of them. One well had twice as much vinyl chloride as is permitted under state drinking water standards.

Advertisement

The study also found evidence of leachate, a liquid that often forms as water moves through waste. The EPA said more investigation will be needed to find out if the leachate, or contaminated water, is limited to shallow depths or is moving toward major ground-water basins. The agency said it found high levels of methane gas on portions of the site, but more study is necessary to determine the extent of the problem.

In a letter to Rep. Martinez, David Howekamp, division director of the EPA regional office in San Francisco, said cleanup will probably require the extraction of landfill gas, leachate and contaminated water.

And, he said, the EPA plans to put gas collection and leachate treatment plants and a cleanup staging area on 30 of the 45 acres. Leachate and landfill gas would be piped from the dump south of the freeway to the treatment plants.

A decision to build a leachate treatment plant on part of the 45 acres was made last year, but it was not until last week that Monterey Park officials learned that the EPA intends to occupy most of the site.

Howekamp said the agency will need 25 acres just to store gravel and dirt and park machinery required to put a 6-foot-thick cover over the entire dump.

Howekamp said that although the EPA will be using 30 acres, the remaining 15 on the north side of the freeway could be made available for development as soon as the land is cleaned up. And, he said, if a developer wants to help pay the cleanup cost, it also might be possible to release other portions of the site early.

Advertisement

Otherwise, he said, development of most of the 45-acre site could not begin until between 1993 and 1995 at the earliest, and the site would not come off the federal Superfund list until the year 2001.

Dermer said the only final decision made by the EPA involves the location of the leachate treatment plant. She said officials are studying what to do with the landfill gas it collects. Options include using the gas to generate electricity or continuing the present practice of burning it.

Dermer said Monterey Park and Montebello officials have agreed it makes sense to put the gas collection system next to the leachate treatment plant, but the final decision on location will not be made until later this year.

She said the EPA looked at sites on the south side of the freeway to store dirt and machinery but could not find sufficient flat land. She said the only suitable site seems to be on the northern parcel.

David Bentz, interim city manager in Monterey Park, said developers are eager to build on the 45 acres but are not willing to assume liability by developing property while it is undergoing toxic cleanup.

“No developer in his right mind would want to touch the property until it comes off the federal Superfund list,” he said, meaning that development is unlikely to begin until 2001.

Advertisement

To help serve the proposed commercial project, Monterey Park had planned to extend Greenwood AveAnue across the freeway to Montebello and work with the state to construct freeway on- and off-ramps. But the EPA said extension of Greenwood would require the excavation of 164,000 cubic yards of waste and relocation of existing gas and leachate control systems, work the agency cannot pay for.

Bentz said Monterey Park does not have the money to pay for the excavation and relocation itself, so unless the EPA changes its position, the Greenwood extension will not be built.

Martinez said he hopes to obtain reversal of the EPA decisions by appealing to EPA officials in Washington. Martinez said that if the EPA had accepted the state and Monterey Park plan two years ago, the property north of the freeway would have been cleaned up by now. Instead, he said, the EPA has undertaken elaborate studies that do not do much more than confirm what was already known about the property.

“EPA doesn’t know what they’re doing,” Martinez said. “They put on a show for the public to make people think they are doing something when they are not.”

But Hank Yoshitake, chairman of Homeowners to Eliminate Landfill Problems, which has fought for cleanup of the dump, said he believes the EPA has been doing a good job.

Although the dump is in Monterey Park, the nearest residents are in Montebello. Yoshitake said putting the leachate treatment plant north of the freeway places it away from homes. He said Monterey Park officials are upset about the site because it is the last large parcel available for commercial development and the city needs sales tax revenue.

Advertisement

Mayor Houseman said his chief concern is not commercial development, but safety. He said pipes will have to be installed over or under the freeway to carry leachate and landfill gas to the treatment and collection center. He said the EPA usually tries to keep toxic waste from spreading but this plan “goes against the whole notion of containing the problem.”

The EPA currently takes leachate from the dump to a treatment plant in Vernon. The agency says that building a plant on the site will save money and assure that treatment facilities will be available in the future. EPA officials have promised to dismantle the plant as soon as it no longer is needed for the dump cleanup.

Dermer said the EPA record of decision establishing the location of the leachate plant prohibits using the plant to treat any leachate that does not come from OII. She said that if the EPA tried to use the plant to treat leachate from other dumps, it could be sued.