Storm Drain Work to Begin in January

Share

The installation of a storm drain in Canoga Park to relieve flooding problems will begin in January, Supervisor Zev Yaroslavsky’s office has announced.

The county Department of Public Works will install more than 3,000 feet of a storm drain system on Saticoy Street beginning at De Soto Avenue and continuing westward to Deering Avenue.

The work will be done under a $575,009 contract awarded to Mladen Grbavac Construction Co. of Arcadia, which was the lowest of eight bidders, Yaroslavsky said in a statement. The project, which is expected to take 60 working days, is due to be completed in April.

Advertisement

Once work begins, existing traffic lanes on the streets may be reduced or closed to through traffic, though local access will be maintained, Yaroslavsky said.