Advertisement

$4.4-Million Bid Approved for Addition to Airport

Share

A $4.4-million addition, twice as expensive as originally estimated, will be built onto the Burbank Airport terminal, even though the terminal is to be demolished sometime in the next few years.

The new East Concourse is part of a change in the airport’s layout mandated by the Federal Aviation Administration because the 56-year-old airport’s terminal is too close to the runways.

The Burbank-Glendale-Pasadena Airport Authority this week approved a bid by the Bernards Bros. Construction Co. to build the concourse and a parking apron for eight jetliners.

Advertisement

The FAA ordered construction of the jetliner apron to place more distance between parked aircraft and those using the runway.

Construction of the 43,000-square-foot concourse had been estimated to cost about $2 million. However, airlines that use the airport--which will pay most of the construction costs--wanted a more elaborate facility, officials said.

Construction begins in February and is to be completed in August.

A new terminal, farther from the runways, is planned for the 1990s.

Advertisement